  • ITTIGI MINI HYDRO ELECTRIC PROJECT

Location :  Tungabhadra River, Hospet Taluk, Bellary   District, Karnataka  State

Capacity :  9 MW

Expected Annual  Generation  :  28.50 MU

Current Status :DPR approved, Irrigation Clearance obtained, Land acquisition is in Progress 

  • ADDANKI MINI HYDRO ELECTRIC PROJECT

Location : Gundlakamma River, Gangannapalem   Village,  Prakasam Dist, Andhra Pradesh

Capacity : 70 cumecs

Expected Annual Generation : 10.7MU

Current Status :DPR submitted to NEDCAP & WRD for Irrigation clearance.

Govt. has issued NOC for the Project.

Request has been sent to NEDCAP for shifting the Project upstream.  Approval Awaited

 

  • YIPPEREVARU MINI HYDRO ELECTRIC PROJECT
  • CHINTMANI MINI HYDRO ELECTRIC PROJECT
  • VIRUPAKESHWARA MINI HYDRO ELECTRIC PROJECT
  • SANGAPURAM MINI HYDRO ELECTRIC PROJECT

Location : Tungabhadra River, Sangapuram Village, Koppal Taluk, Koppal District, Karnataka State.

Combined Capacity :  13.8 MW

Current Status :Govt Order received for implementation of projects.   

Preparation of DPR is under progress. 

B & G RENEWABLE ENERGY PVT LTD

UPPER GANGA CANAL SMALL HYDRO POWER PROJECT

Location :   Nirgajini Village, Uttar Pradesh state
Capacity :   3 x 2.5 MW

 

Location :   Chitaura Village, Uttar Pradesh state
Capacity :   3 x 2 MW

 

Location :   Salawa Village, Uttar Pradesh state
Capacity :   2 x 2.475 MW

Current Status :

      i. Common for all the three above Projects – As given below

 

      ii. Revised DPR approved by UPJVNL

 

      iii.NOC obtained from Irrigation Department

 

      iv. Bids (NCB) received for Civil and H&M Works and Agency finalised

 

    v. For E & M, ICBs received and Agency finalised

 

Chamundeeswari Energy Pvt. Ltd
    • AJRI MINI HYDRO ELECTRIC PROJECT
      Location :   Kubja River, Ajri village, Udupi District, Karnataka State
      Capacity :   3 MW

      Current Status :
      Govt Order received for implementation of project.
      MOU signed with Govt of Karnataka
      Forest clearance awaited for undertaking Survey

    • CHIKOTHANHADI MINI HYDRO ELECTRIC PROJECT
      Location :   Kubja River, Chikothanhadi village, Udupi District, Karnataka State
      Capacity :   3 MW

      Current Status :
      Govt Order received for implementation of project.
      MOU signed with Govt of Karnataka
      Forest clearance awaited for undertaking Survey

    • MUDUGAL MINI HYDRO ELECTRIC PROJECT
      Location :   Kubja River, Hanchekatte village, Udupi District, Karnataka State
      Capacity :   3 MW

      Current Status :
      Govt Order received for implementation of project.
      MOU signed with Govt of Karnataka
      Forest clearance awaited for undertaking Survey

    • HALLIHOLE MINI HYDRO ELECTRIC PROJECT
      Location :   Chakra River, hallihole village, Udupi District, Karnataka State
      Capacity :   3 MW

      Current Status :
      Govt Order received for implementation of project.
      MOU signed with Govt of Karnataka
      Forest clearance awaited for undertaking Survey

    • GULVADI MINI HYDRO ELECTRIC PROJECT
      Location :   Chakra & Kubja Rivers, Kodaladi and Goratte village, Udupi, District, Karnataka State
      Capacity :   3.2 MW

      Current Status :
      Govt Order received for implementation of projects.
      Forest clearance awaited for undertaking Survey

  • GOWBACHA MINI HYDRO ELECTRIC PROJECT
    Location :   Narmada River, Jillharighat village,Shahpura Tehsil, Jabalpur Dist, Madhya Pradesh State
    Capacity :   4 MW

    Current Status :
    Pre feasibility report submitted and project got allotted.
    MOU and HPDA signed. DPR (10 MW) is submitted to NRED for approval.

SAS Hydel Projects Pvt. Ltd

SARSUMA MINI HYDRO ELECTRIC PROJECT 

Location : Sonar river, Himmatpati village, Damoh Dist, Madhya Pradesh State
Capacity : 9.75 MW

Current Status :
Successfully Commissioned on 8th August 2018